Sl.No Location
No.of Houses
HIG MIG LIG Total
Project Cost in Lakhs Date of Commencement of Scheme Percentage Of Work Completed Probable date of completion
SOUTH DIVISION
1 Laksmiguda 80 0 0 80 3790.24 15.11.2010  100% 14.09.2012
  TOTAL 80 0 0 80 3790.24    
WESTEREN DIVISION
2 Kukatpally,Ph IV 0 0 630 630 4914.00 09.03.2011 100% 31.03.2013
3 Chandanagar 0 0 30 30 1036.50 06.09.2010 40.49% 05.11.2013
4 Kukatpally,Ph XV 180 0 0 180 9714.60 08.02.2011 32% 15.10.2013
5 Sadasiva Pet 12 13 0 25 831.00 26.06.2011 21.64% 31.08.2013
  TOTAL 192 13 660 865 23538.00    
NORTH DIVISION
6 Nizampet 0 0 90 90 2280.30 03.01.2011 98% 31.05.2013
  TOTAL 0 0 90 90 2280.30    
MAHBOOBNAGAR DIVISION
7 Pargi, RR Dist. 0 15 0 15 391.638 9.8.2010 100% 10.11.2012
8 Dev. Plots at Wanaparthy, Mahaboobnagar Dist. 0 104 236 340 388.53 28.9.2010 100% 31.01.2013
9 Gadwal. 75 130 125 130 3180.29 29.11.2011 100% 31.01.2013
10 Devarakonda Road, Nalgonda. 170 167 0 337 5840.70   7% 17.01.2015
11 Jadcherla, MBNR Dist. 0 0 50 50 602.86 07.03.2013 5% 06.03.2014
  TOTAL 245 401 426 1072 10404.02    
WARANGAL DIVISION
12 Jagityal,Warangal 0 24 0 24 222.72 08.07.2010 100% 07.04.2012
13 GOrrekunta, Ph-IV 0 35 0 35 322.08 24.02.2011 100% 31.10.2012
  TOTAL 0 59 0 59 544.80    
NIZAMABAD DIVISION
14 Sawargaon, Adilabad, Ph-V 0 0 70 70 527.80 18.12.2012 30% 17.06.2014
  TOTAL 0 0 79 70 527.80    
KURNOOL DIVISION
15 Joharapuram,Kurnool 46 80 0 126 912.83 25.02.2012 100% 24.06.2012
16 Nandyal. Ph-VII & VIII 36 56 0 92 1445.00 31.08.2010 85% 30.09.2013
17 Proddatur, Ph-V 0 17 47 64 1072.34 01.06.2012 50% 31.12.2013
  TOTAL 82 153 47 282 3430.17    
VIJAYAVADA DIVISION
18 Machilipatnam - Phase II 0 40 2 42 582.32 22.05.2012 2% 30.04.2014
19 Bhavanipuram ,Vijayawada 0 90 0 90 1763.00 24.08.2010 84% ( with Price Adjust-ment) 15.09.2013
  TOTAL 0 130 2 132 2345.32    
TADEPALLIGUDEM DIVISION
20 Narsapur, WG Dist 0 9 4 13 115.84 01.09.2010 98% 30.06.2013
  TOTAL 0 9 4 113 115.84      
VISHAKAPATTANAM DIVISION
21 Madhurawada , LIG (260 flats actually taken-up) 0 0 480 480 1585.50 17.07.2009 100% 31.07.2012
22 Madhurawada (120 + 40)  120 120 0 240 6896.00 11.08.2010 100% 30.11.2012
  TOTAL 120 120 480 720 8481.50      
NELLORE DIVISION
23 Kallurupalli,Nellore 20 152 0 172 1997.00 28.07.2010 100% 31.05.2013
24 Tada 0 12 30 42 322.80 21.11.2012 25% 20.05.2014
  TOTAL 20  164 30 214 2319.00      
  GRAND TOTAL 739 1049 1739 3527 57250.09      
 
 

  Applications are invited for allotment Row houses ( G+1) to be taken up under Self Financing Scheme near Irukalala Parameswari Temple,Nellore town...... ..

  Flats for sale on first cum first served basis at Sanskruti (Singapore Class)Township at Pocharam... ..
  The payment schedule of (iv) & (v) installments in respect of 1400 sft (Sampoornam) flats under phase-XV, venture –III at Kukatpally, are herby further extended... ..
  Applications are invited for dispose of vacant houses / flats at Medak and Nagaram on hire purchase / out right sale..
 
Home | About Us | GOs and Rules | Download | Organization Structure | Site Map | Contact Us | APHB Mail | EMS Login | Administration
Copyright © Andhra Pradesh Housing Board. All Rights Reserved.