  Ongoing Projects  
 
Sl.No Location
No.of Houses
HIG MIG LIG Total
Project Cost in Lakhs Date of Commencement of Scheme Percentage Of Work Completed Probable date of completion
MAHBOOBNAGAR DIVISION
1 Pargi, RR Dist. 0 15 0 15 391.638 9.8.2010 10% 8.8.2011
2 Dev. Plots at Wanaparthy, Mahaboobnagar Dist. 0 104 236 340 388.53 28.9.2010 Work Commenced. 27.9.2011
3 Gadwal. 75 130 125 130 3180.29 29.11.2011 5% 28.5.2012
KURNOOL DIVISION
4 Joharapuram,Kurnool 46 80 0 126 912.83 1.10.09 48% 24.8.2011
5 Nandyal. Ph-VII & VIII 36 56 0 92 1445.00 8.7.2010 20% 7.7.2011
6 Dev. Plots At Guntakal Ananthapur Dist. 131 0 130 261 510.96 21.6.2010 50% 31.05.2011
NORTH DIVISION
7 Officers Quarters at Kundan Bagh,Hyd. 45 0 0 45 2827.00 26.5.2008 95% 30.4.2011
8 Flats At Nizampet Quitbullapur. 0/td> 0 90 90 2280.30 29.9.2010 Work Commenced 28.12.2011
WESTEREN DIVISION
9 LIG Flats At Kukatpally Ph-IV (460 sft- 252 nos & 580 sft-378 no) 0 0 630 630 4914.00 9.3.2010 25% 8.9.2011
10 Flats at Chandanagar, RR Dist.. 0 0 30 30 1036.50 6.9.2010 5% 5.9.2011
11 HIG Flats at Kukatpally Ph-XV (1400 sft - 180/270 nos). 180 0 0 180 9714.60 8.2.2011 Work Commenced 7.8.2012
SOUTH DIVISION
12 Laksmiguda 80 0 0 80 3790.24 25.1.2011 Work Commenced 24.1.2012
CENTRAL DIVISION - NILL
WARANGAL DIVISION
13 Development of Plots at Gorrekunta, Warangal Dist. 82 0 0 82 174.34 28.7.2009 100% 31.1.2011
14 Jagityal,Warangal 0 0 24 24 222.72 8.7.2010 25% 7.7.2011
15 GOrrekunta, Ph-IV 0 33 0 33 322.08 24.2.2010 15% 23.2.2012
NIZAMABAD DIVISION
16 Sawargoan, Adilabad Dist. 0 0 15 15 96 9.8.2010 30% 8.5.2011
NELLORE DIVISION
17 Kallurupalli,Nellore 20 152 0 172 1997.00 28.7.2010 10% 27.7.2011
18 Putlampalli Kadapa. 377 94 0 471 8399.58 28.2.2009 90% 31.3.2011
VISHAKAPATTANAM DIVISION
19 Krishnarayapuram , Visakhapatnam 0 66 0 66 334.20 18.7.2009 99% 31.3.2010
20 Madhurawada, Vizag. 0 0 480 480 1585.50 24.7.2009 75% 30.09.2011
21 Madhurawada, Vizag. 120 120 0 240 6896.00 11.8.2010 20% 10.12.2011
VIJAYAVADA DIVISION
22 Bhavanipuram ,Vijayawada 0 0 600 600 2107.50 2.4.2007 95% 30.4.2010
23 Machilipatnam 0 213 0 213 2320.75 13.5.2009 77% 15.4.2011
24 Bhavanipuram ,Vijayawada 0 90 90 180 1763.00 24.8.2010 Work Commenced 31.8.2011
TADEPALLIGUDEM DIVISION
25 Narsapur, WG Dist 0 9 4 13 115.84 7.7.2010 5% 30.9.2011
26 Rajamundry, East Godavari District. 0 12 8 20 214.00 3.7.2010 35% 31.8.2011
 
 

EMPANELMENT OF ARCHITECTS.
  Notification.
  Eligibility_and_insrtuctions.
  Annexures.

Applications for allotment of the Single Bed Room Flats near Rain Tree Park, Kukatpally,Hyd.
Applications for allotment of the prime areas for office accommodation/shops/garages on monthly rental basis through Sealed Tender cum Open Auction.
    Applications Form  

 
Home | About Us | GOs and Rules | Download | Organization Structure | Site Map | Contact Us | APHB Mail | EMS Login | Administration
Copyright © Andhra Pradesh Housing Board. All Rights Reserved.